Arthur Street Utility Extension

Background

Arthur Street is a 2-lane paved rural roadway with ditches from 129th Avenue to 333 feet south of Fawn Trail. There is a storm sewer within the Arthur Street right-of-way on the west side of the road between 13125 and 13225 Arthur Street. None of the homes are served by sanitary sewer or watermain and some are known to have failing septic systems. There is a public sanitary sewer and water main near the project area on 129th Avenue and Fawn Trail. There is underground power and cable along the west side of Arthur Street.

The proposed improvements include the installation of sanitary sewer on Arthur Street from 129th Avenue to 620 feet north of 129th Avenue and from Fawn Trail to 650 feet south of Fawn Trail. Watermain will also be installed from Fawn Trail to the Arthur Street cul-de-sac. These improvements are consistent with the City's Comprehensive Plan and the proposed project is feasible, necessary, and cost-effective from an engineering standpoint.

Project Map & Location

Updates

  • 1-26-24  2024 sealed bids were opened for the Arthur Street Utility Improvements Project. 

    • The lowest bid was submitted by Northern Lines Contracting.  The Rogers City Council awarded the contract to them at the February 13, 2024, City Council meeting.

Timeline

Construction on the project is anticipated to begin the week of May 27, 2024. The scheduled completion date for the project is the end of July 2024. 

The general sequence of construction for each stage will be as follows:

  • Installation of Erosion Control Items

  • Removal of Topsoil

  • Removal of Existing Pavement and Curb (as needed)

  • Installation of Sanitary Sewer

  • Installation of Water Main

  • Roadway Construction-Including:

    • Grading of roadway base

    • Installation of curb and gutter

    • Installation of gravel/aggregate base

    • Installation of bituminous paving

  • Initial Boulevard Grading

  • Placement of Topsoil, Final Boulevard Grading and Seeding Boulevard

Key Documents